Road Network:
KKH Phase II (Thakot -Havelian Section)
- Work initiated in September, 2016.
- Contractor began work.
- Will be finished by March 2020.
- Havelian- Abbotabad-Mansehra (39 KM approx) section will be delivered by May, 2018
KKH Thakot-Raikot N35 remaining portion (136 Km)
- Feasibility and PC-I finished
- LOI communicated to Chinese side
- Procedural formalities will be delivered shortly
Peshawar-Karachi Motorway
- Construction works began in August, 2016.
- Contractor work commenced.
- 129 km Multan- Tranda M. Panah (Bahawalpur) section to be completed by Mid of 2018.
- 125 km Sukkur- Sadiqabad section to be completed by Mid of 2018.
- 04 out of 07 sections to be completed by Mid of 2018.
- Completion planned in Auguest 2019.
Khuzdar-Basima Road N-30 (110 km)
- Feasibility and PC-I finished
- LOI communicated to Chinese side
- Procedural formalities to be delivered shortly (ECNEC approved the projects in May 2017)
- FWA (Frame Work Agreement) communicated with Chinese Side